CCAMTG-2500 A04 — Commissioning & Performance Acceptance

Volume 18 defines the complete commissioning and performance-acceptance architecture for the CCAMTG-2500 A04, taking the assembled and installed machine from documented pre-start readiness through first energization, active magnetic-bearing levitation, first rotation, charge-mode proving, generation-mode proving, protective-function testing, mode-transition testing, rated performance verification, formal acceptance and final handover.

Main Public Commissioning Baseline

A04 Commissioning Status: Public baseline values identify the current A04 engineering configuration. Final certified test tolerances, instrument-accuracy classes, safety-trip setpoints, vibration limits, pressure-test values, grid settings and supplier-specific acceptance criteria remain governed by approved calculations, certified supplier data, hazard review and jurisdictional requirements.

Commissioning Scope

Integrated Test Boundary

Commissioning Release Gates

Commissioning Responsibilities

Test Equipment & Data Quality

Pre-Commissioning Checks

Valve & Final Element Verification

Electrical Pre-Start Testing

Controls & SIS Pre-Start Testing

First AMB Levitation

First Rotation

Charge-Mode Commissioning

Charge-Mode Energy Path

Generation-Mode Commissioning

Generation-Mode Energy Path

Rated Performance Testing

Mandatory Performance Data

Public Performance Acceptance Targets

Performance Data Reduction

Data Integrity Rules

Protective-Function Testing

Safe Protection Test Philosophy

Mode Transition Testing

Turndown & Dynamic Testing

BESS, PCS & Grid Functional Acceptance

Pressure-System Acceptance

Acceptance Decision Logic

Commissioning Punch List

Commissioning Records & Final Dossier

End-to-End Commissioning Sequence

V18 Commissioning Package

Commissioning Release Philosophy