CCAMTG-2500 A04 — Commissioning & Performance Acceptance
Volume 18 defines the complete commissioning and performance-acceptance architecture for the CCAMTG-2500 A04,
taking the assembled and installed machine from documented pre-start readiness through first energization,
active magnetic-bearing levitation, first rotation, charge-mode proving, generation-mode proving,
protective-function testing, mode-transition testing, rated performance verification, formal acceptance
and final handover.
Main Public Commissioning Baseline
- Machine Class: 2.5 MW-Class Dual-Mode Compressed-Air Energy Storage / Recovery Magnetic Motor-Generator Machine
- Net AC Generation Target: 2.50 MW
- Nominal Rotor Speed: 12,000 rpm
- Master Air Mass Flow: 12.2 kg/s
- Compression Range: 1.20 bara → ~31 bara
- Expansion Range: ~31 bara → 1.20 bara
- DC Bus: 1,500 VDC
- BESS Energy Capacity: ~5 MWh LFP
- Dry Skid Mass (Estimated): ~22,000 kg
A04 Commissioning Status:
Public baseline values identify the current A04 engineering configuration. Final certified test tolerances,
instrument-accuracy classes, safety-trip setpoints, vibration limits, pressure-test values, grid settings
and supplier-specific acceptance criteria remain governed by approved calculations, certified supplier data,
hazard review and jurisdictional requirements.
Commissioning Scope
- Pre-commissioning readiness
- Mechanical completion verification
- Pressure-system release
- Electrical energization readiness
- Controls and SIS functional proving
- AMB levitation
- First rotation
- Charge-mode commissioning
- Generation-mode commissioning
- Rated performance testing
- Protective-function testing
- Mode-transition testing
- FAT and SAT integration
- Final acceptance and handover
Integrated Test Boundary
- Air intake and conditioning system
- Three-stage compressor
- HP buffer vessel
- Three-stage turbine
- Active magnetic bearings
- Touchdown-bearing system
- Thermal, cooling and TES systems
- Structural skid and foundation interface
- Electrical power conversion
- Fasteners, joints and sealing
- PLC, SIS, HMI and SCADA
- External compressed-air storage
- BESS, PCS and grid systems
Commissioning Release Gates
- Document readiness
- Mechanical completion
- Pressure-system release
- Electrical energization release
- Controls and SIS release
- AMB levitation release
- First-rotation release
- Charge-mode process release
- Generation-mode process release
- Rated performance release
- Acceptance and handover
Commissioning Responsibilities
- Commissioning management
- Mechanical systems leadership
- Electrical systems leadership
- Controls and SIS leadership
- Rotating equipment and AMB specialists
- Process and thermal engineering
- Safety and hazard-review representation
- Independent witnessing where required
Test Equipment & Data Quality
- Acceptance measurements use calibrated and traceable instruments
- Calibration validity covers the test period
- Pressure channels are zeroed and verified
- Redundant airflow channels are cross-checked
- Temperature channels are validated
- Redundant rotor-speed channels are reconciled
- AMB rotor-position and vibration signals are validated
- Electrical power measurements are synchronized across machine boundaries
- Cooling-system flow and temperature data are recorded
Pre-Commissioning Checks
- Verify equipment tags and serial numbers
- Verify installed configuration against the controlled A04 baseline
- Verify structural skid and foundation condition
- Verify rotor alignment and coupling records
- Verify rotor balance and runout records
- Verify critical bolted-joint records
- Verify pressure-boundary material and NDE records
- Verify cleanliness and foreign-material exclusion
- Verify process and cooling circuits are ready
- Verify electrical terminations, segregation and earthing
- Verify instrument calibration and loop readiness
- Verify emergency-stop and fire interfaces
Valve & Final Element Verification
- External storage isolation stroke and fail-state verification
- Turbine inlet control stroke and fail-state verification
- Compressor discharge isolation verification
- Anti-surge recycle fail-open verification
- Reheater isolation verification
- Buffer blowdown verification
- Reverse-flow protection verification
- Position feedback and proof-of-state checks
Electrical Pre-Start Testing
- Control-power and UPS verification
- DC precharge sequence verification
- Converter functional testing
- Electrical protection injection testing
- Insulation and earthing verification
- Switchgear and isolation verification
- PCS and converter readiness checks
- Electrical interlock verification
Controls & SIS Pre-Start Testing
- I/O point-to-point checks
- Loop checks
- Permissive verification
- Interlock verification
- Alarm and trip verification
- Cause-and-effect functional testing
- HMI indication verification
- SCADA and historian verification
- Time synchronization checks
- Emergency-stop sequence verification
First AMB Levitation
- Establish control power
- Establish machine cooling
- Verify emergency-stop health
- Verify high-pressure system is in a safe startup state
- Enable the AMB controller with the rotor stationary
- Levitate and centre the rotor
- Verify radial rotor-position channels
- Verify axial position channels
- Verify no AMB instability or saturation
- Verify touchdown-bearing readiness
First Rotation
- Complete DC bus precharge
- Enable the inverter in a controlled no-load state
- Apply minimum approved torque
- Verify direction of rotation
- Verify redundant rotor-speed agreement
- Verify no rub or unintended mechanical contact
- Monitor rotor position and vibration
- Monitor AMB current and temperature
- Increase speed only through approved commissioning hold points
- Critical-speed progression follows the approved rotor-dynamic plan
Charge-Mode Commissioning
- Establish AMB levitation and cooling
- Precharge the DC bus
- Enable PMSM motor operation
- Establish compressor flow with protective recycle initially open
- Increase rotor speed under approved surge-margin control
- Progressively reduce recycle after stable flow develops
- Prove compressor stage pressure rise
- Enable staged intercooling
- Enable TES heat capture
- Progress toward the public rated speed and flow baseline
- Verify stable unloading and return to standby or stop
Charge-Mode Energy Path
- Grid and/or BESS electrical energy
- Bidirectional PCS and inverter
- PMSM motor operation
- Common rotor
- Three-stage compressor
- Intercoolers and thermal-energy recovery
- HP buffer vessel
- External compressed-air storage
Generation-Mode Commissioning
- Verify external compressed-air storage availability
- Verify TES preheat and reheat availability
- Establish AMB, cooling and DC-system readiness
- Isolate the compressor high-pressure path
- Open turbine inlet under controlled ramping
- Enable turbine preheat and interstage reheating
- Transition the PMSM/PMG from motoring toward generation
- Increase rotor speed and electrical export under controlled conditions
- Verify stable turbine stage behavior
- Progress to the 2.50 MW net AC public design target under defined test conditions
Generation-Mode Energy Path
- External compressed-air storage
- HP buffer vessel
- Turbine inlet control
- TES preheater
- Three-stage reheated turbine
- Common rotor
- PMG generation
- Active rectifier and DC bus
- BESS and/or grid interface
Rated Performance Testing
- All required commissioning gates released before formal testing
- No unresolved safety-critical punch items
- Approved compressor and turbine performance maps available
- Approved thermal and electrical design inputs available
- Test instruments calibrated and synchronized
- Ambient and boundary conditions recorded
- Stable operation established before the formal test window
- Actual and corrected results reported separately
- Measurement uncertainty included in the acceptance logic
Mandatory Performance Data
- Ambient conditions
- External storage condition
- TES condition
- Rotor speed
- Rotor position and vibration
- Main airflow
- Compressor pressure and temperature states
- Turbine pressure and temperature states
- Thermal-system data
- Cooling-system data
- PMG and converter electrical data
- DC bus voltage, current and power
- Grid AC power and energy
- BESS power and state-of-charge
- Valve positions and control commands
Public Performance Acceptance Targets
- Nominal Rotor Speed: 12,000 rpm
- Main Air Mass Flow: 12.2 kg/s
- Compression: 1.20 bara → ~31 bara
- Expansion: ~31 bara → 1.20 bara
- Net AC Generation Target: 2.50 MW
- DC Bus: 1,500 VDC
- Stable mode transition without uncontrolled rotor, pressure or electrical excursion
- Protective functions verified through safe and approved test methods
Performance Data Reduction
- Measured and calculated values reported separately
- Measurement uncertainty reported separately
- Redundant airflow channels reconciled
- Compressor pressure ratios reconciled to approved maps
- Charge-mode electrical and shaft power reconciled
- Turbine gross-power performance reconciled
- Net AC export reconciled
- Thermal-energy balance reconciled
- DC and AC conversion losses reconciled
- Round-trip performance calculated only over a defined charge/storage/generation cycle
Data Integrity Rules
- Raw test and historian data are retained
- Unfavourable data are not manually removed without documented justification
- Processed results identify calculation methods and software versions
- Sensor substitution or calibration drift is documented
- Channel disagreement is documented
- Test interruptions and trips are logged
- Operator interventions are logged
- BESS, grid and thermal constraints are recorded
Protective-Function Testing
- Overspeed protection
- AMB instability response
- High-vibration shutdown
- Buffer overpressure response
- Cooling-failure response
- Electrical-fault response
- Fire and emergency-stop response
- Valve loss-of-actuation fail-state verification
- Independent mechanical pressure relief remains available
Safe Protection Test Philosophy
- Protection logic is verified by approved simulation or injection where possible
- Destructive overspeed testing is not assumed
- AMB fault testing avoids destructive rotor contact
- Pressure protection is verified without defeating independent mechanical relief
- Electrical protection uses approved injection and simulation methods
- Emergency sequences follow the approved hazard-study philosophy
Mode Transition Testing
- Standby to charge
- Charge to standby or stop
- Standby to generation
- Generation to standby or stop
- Controlled charge-to-generation transition where permitted
- Controlled generation-to-charge transition where permitted
- Inactive process paths remain isolated during transitions
- No unstable rotor, pressure or electrical excursion is permitted
Turndown & Dynamic Testing
- Approved operating-range verification
- Compressor map compliance
- Turbine map compliance
- Anti-surge transient testing
- Cooling pump duty/standby changeover
- Electrical load transition testing
- Dynamic control response verification
BESS, PCS & Grid Functional Acceptance
- BESS operating-state logic verification
- PCS bidirectional charge and discharge verification
- Grid synchronization verification
- Grid protection verification
- Power-quality verification
- Electrical insulation monitoring verification
- BMS authority and battery protection retained
- Final grid and battery safety settings remain supplier and site controlled
Pressure-System Acceptance
- Pressure-boundary records verified before operation
- Redundant buffer pressure instrumentation functionally proven
- Independent mechanical relief certification verified
- Controlled blowdown and depressurization tested
- External storage isolation fail-safe behavior proven
- Reverse-flow prevention proven
- Machine remains inside the approved pressure and temperature envelope
Acceptance Decision Logic
- PASS — mandatory safety and functional tests passed and approved performance criteria achieved
- PASS WITH OPEN NON-BLOCKING ITEMS — only formally accepted non-safety and non-performance items remain
- RETEST REQUIRED — data quality, stability, instrumentation or performance issues require repeat testing
- FAIL / HOLD — safety, pressure, rotor, protection, surge or uncontrolled-excursion issue prevents acceptance
Commissioning Punch List
- Unique punch-item identification
- Originating date and test package
- Affected subsystem and tag
- Objective description of open work
- Blocking or non-blocking classification
- Controlling requirement source
- Immediate disposition
- Responsible owner and due gate
- Corrective action
- Verification or retest evidence
- Formal closure approval
Commissioning Records & Final Dossier
- Approved commissioning procedures
- Design baseline and ECN records
- Mechanical completion records
- Pressure-system and relief records
- Electrical test records
- Instrumentation calibration records
- Controls and SIS test records
- AMB and rotating-equipment commissioning records
- Charge and generation process data
- Thermal and cooling-system records
- Raw and processed performance data
- Uncertainty statement
- Punch-list and retest records
- Training and handover records
- SAT and as-built references
End-to-End Commissioning Sequence
- Freeze the commissioning baseline and approved changes
- Release mechanical completion and QA/NDE traceability
- Release pressure-system certification and relief protection
- Complete electrical and control-power checks
- Calibrate instruments and complete I/O checks
- Prove valve fail states and SIS cause-and-effect
- Prove cooling and thermal packages
- Perform stationary AMB levitation
- Complete DC precharge and no-load converter checks
- Perform first rotation
- Perform charge-mode proving
- Perform generation-mode proving
- Perform dynamic and abnormal-case tests
- Perform BESS, PCS and grid acceptance
- Perform performance data reduction and uncertainty review
- Retest deviations and close blocking punch items
- Complete final acceptance, handover and as-built dossier integration
V18 Commissioning Package
- Commissioning Plan
- Performance Test Procedure
- Commissioning Punch List Template
- Pre-start readiness requirements
- Release-gate architecture
- First levitation and first-rotation procedures
- Charge-mode proving procedure
- Generation-mode proving procedure
- Protective-function test matrix
- Mode-transition and dynamic-test requirements
- Performance acceptance and closeout framework
Commissioning Release Philosophy
- Commissioning proves the complete machine as an integrated system
- Both charge and generation energy paths must be demonstrated
- Inactive process paths must remain safely isolated
- Independent protection layers remain available during testing
- Test data are retained and traceable
- Approximate concept values are not silently converted into acceptance tolerances
- Final acceptance values remain tied to approved calculations, supplier data and hazard studies
- No blocking safety or performance item remains open at final handover