H.E.R.P.S — FAT, SAT, Commissioning & Performance Acceptance

HERPS-VOL-22 — Revision D R2.0

Hybrid Energy Recovery Pump System (H.E.R.P.S)

Revision D Acceptance & Commissioning Program

HERPS-VOL-22 defines the factory acceptance testing, site acceptance testing, commissioning sequence, performance verification, acceptance records and release-signature requirements for the H.E.R.P.S Hybrid Energy Recovery Pump System.

The acceptance program covers dimensional verification, hydrostatic testing, hydraulic Q-H performance, efficiency, power, NPSHR, vibration, bearing temperature, electrical protection, recovery-mode operation, BESS and DC systems, thermal management, instrumentation, trips, interlocks, commissioning and signed acceptance records.

Revision D R2.0 Acceptance Baseline

Acceptance Parameter Revision D R2.0 Basis
Machine 160 kW-drive-class horizontal three-stage variable-speed centrifugal industrial water pump with controlled hydraulic-energy-recovery path
Rated Process Flow 150 L/s — 540 m³/h
Rated TDH 80 m water
Rated Speed 2,900 rpm
Operating Envelope 1,500–3,600 rpm subject to released exclusion map
Pressure Boundary 25 bar(g), 80 °C design baseline
Hydrotest 37.5 bar(g) baseline subject to approved governing code/material factors
Recovery Flow Up to 150 L/s at 6.75 m available head
Nominal Recovery Output Target Approximately 8.25 kW net electrical at the nominal genuine recovery condition
Cooling 6 m³/h nominal main loop; 40 kW radiator
DC Link 750 VDC nominal; 650–800 V controlled
BESS 192S, 160 Ah, 614.4 V nominal, 98.304 kWh
Supercapacitor 750 V, 16 F nominal
Package Envelope 10,400 × 2,600 × 2,400 mm maximum

Evidence-Based Acceptance Philosophy

Factory Acceptance Test Preconditions

FAT Sequence & Hold Points

Step Factory Activity
FAT-01Document and configuration verification
FAT-02Dimensional and as-built survey
FAT-03Mechanical inspection, rotor free rotation, alignment and guards
FAT-04Hydrostatic and leak tests
FAT-05Electrical continuity, insulation, bonding and phase/drive checks
FAT-06Control I/O, permissive, trip and interlock simulation
FAT-07Cooling-loop fill, flush, flow and thermal functional checks
FAT-08No-load / low-load rotation and speed sweep
FAT-09Pump hydraulic performance and NPSHR testing
FAT-10Recovery turbine / PMG / rectifier testing
FAT-11BESS / DC-DC / supercapacitor / DC-link testing
FAT-12Integrated thermal/load endurance run
FAT-13Final trip tests and controlled shutdown
FAT-14Post-test inspection and NCR closure
FAT-15Signed FAT certificate and shipment release

Dimensional & Physical Acceptance

Survey Item Acceptance Requirement
Complete Envelope≤10,400 L × 2,600 W × 2,400 H mm
Structural Base10,400 L × 2,400 W × 300 mm deep baseline
Pump / Motor ShaftY = 0; Z = +800 mm
Turbine / Generator ShaftY = +950; Z = +850 mm
Main Discharge HeaderY = +850; Z = +1,300 mm
Main SuctionY = 0; Z = +800 mm
Pump / Motor Coplanarity≤0.25 mm before shims
Base Mounting Flatness≤0.10 mm across each foot set
Final Parallel Alignment≤0.05 mm
Final Angular Alignment≤0.05° with approved hot-growth correction

Mechanical, Hydrostatic & Leak Testing

Pump Hydraulic Performance — Q-H, Efficiency & Power

Hydraulic performance testing establishes the measured pump curve using water with documented density and temperature. Flow, suction pressure, discharge pressure, speed, power and temperature are recorded across sufficient operating points to establish the Q-H, efficiency and power characteristics.

NPSHR & Cavitation Performance Testing

Measured NPSHR is established using an approved ISO/project method and correlated with the hydraulic design. Final site NPSHA margin is based on measured performance, not a text-only design value.

Vibration, Rotordynamic & Bearing-Temperature Acceptance

Motor, AFE/VFD & Electrical Protection FAT

Hydraulic Energy-Recovery FAT

The direct DN300 and recovery DN300 paths operate in parallel and rejoin downstream. Testing verifies the hydraulic relationship: Qpump = Qdirect + Qrecovery.

BESS, Bidirectional DC/DC & High-Voltage Safety FAT

Parameter Acceptance Basis
Pack192S, 160 Ah, 614.4 VDC nominal, 98.304 kWh
Module Baseline12 × 16S modules
Continuous DC/DC PowerNominally 150 kW subject to certified limits
Peak Power200 kW ≤30 s only where supplier/BMS certification permits
SOC Window10–90% baseline unless approved supplier limits differ
SafetyBMS, IMD, contactors, precharge, HVIL, alarms and emergency isolation verified

Supercapacitor & DC-Link Transient FAT

Thermal-Management FAT

Test Item Acceptance
Main Cooling Flow6 m³/h nominal
Low-Flow Alarm<4.5 m³/h baseline
Low-Flow Trip<3.5 m³/h after validated delay
Radiator40 kW nameplate minimum at project ambient after corrections
PHE40 kW baseline
Reservoir80 L
Expansion Tank50 L
Motor Coolant Inlet25–35 °C target where test conditions permit
Coolant High Alarm45 °C baseline
Coolant High-High Trip55 °C or lower OEM limit

Instrumentation & I/O Verification

Trip, Interlock & Cause-and-Effect Acceptance

Condition Revision D Baseline
Pump Overspeed>3,750 rpm baseline — immediate VFD torque inhibit
Turbine OverspeedReleased hardware trip; preliminary controlled ceiling subject to final release
Discharge High-High≥11 bar(g) baseline
Bearing High-High≥95 °C or lower supplier limit
Vibration High-High7.1 mm/s RMS baseline pending final machine-class setting
Cooling Low Flow<3.5 m³/h sustained
DC-Link Overvoltage≥820 VDC baseline
BESS Insulation FaultOpen BESS contactors; preserve grid pump operation where safe

Every required cause and effect must be physically observed, timed and recorded. PLC or HMI indication alone is insufficient for hardwired safety functions.

Integrated FAT Endurance Run

Site Acceptance Test Preconditions

Site Mechanical & Electrical Acceptance

Controlled Commissioning Sequence

  1. Verify permits, LOTO boundaries and signed mechanical/electrical completion.
  2. Flood and vent the pump/suction system as required and verify seal-flush and cooling availability.
  3. Place the recovery path in safe bypass/direct mode.
  4. Energize control power and verify PLC/HMI, E-stops, BMS, drives, instrumentation and communications.
  5. Energize auxiliaries and establish cooling flow.
  6. Confirm final motor rotation.
  7. Start the pump at controlled low speed without deadhead or hydraulic shock.
  8. Increase speed and load in defined steps while recording hydraulic, vibration, thermal and electrical data.
  9. Establish stable process duty and compare against FAT performance.
  10. Enable and tune automatic flow/pressure control within approved limits.
  11. Introduce recovery gradually only when genuine recoverable downstream pressure is available.
  12. Verify Qpump = Qdirect + Qrecovery without compromising process duty.
  13. Exercise normal stop, controlled trip, emergency stop and restart.
  14. Complete the required endurance period and close the commissioning punch list.

Site Performance Acceptance

Performance Calculation & Data-Reduction Rules

Hydraulic Power: Ph = ρgQH

Revision D rated hydraulic-power reference: 117.48 kW at 998 kg/m³, 0.15 m³/s and 80 m.

Pump efficiency is determined from measured hydraulic power divided by measured shaft power. Where electrical input is used, validated motor and drive losses must be explicitly accounted for.

Recovery Hydraulic Power: Prec,h = ρgQrecHrec

Nominal Revision D recovery hydraulic-power reference: 9.91 kW at 150 L/s and 6.75 m.

Net recovered electrical power is measured at the defined electrical boundary. Recovery energy must not be credited twice and must not be represented as self-sustaining energy.

Acceptance Records & Traceability

Final Acceptance & Release

Final HERPS acceptance requires completion of the applicable factory and site tests, closure or formal disposition of non-conformances, approved as-built records, commissioning records, performance results and required release signatures.

Shipment is released only after mandatory FAT hold points and documentation are complete. Final operating acceptance additionally requires successful SAT, commissioning and performance verification under the actual approved site conditions.

Revision D Engineering Status

HERPS-VOL-22 Revision D R2.0 is the master design-development acceptance and commissioning control volume. Final acceptance remains subject to closure of the applicable D-G1 through D-G18 engineering gates and the approved FAT, SAT, commissioning and as-built records.

Validation-controlled values, supplier limits, site-specific protection settings, measured NPSHR, final machine-class vibration limits and other controlled acceptance parameters are not replaced by unverified design targets.

Explore the Complete H.E.R.P.S Revision D System

FAT, SAT, Commissioning & Performance Acceptance forms part of the complete H.E.R.P.S Revision D multi-volume conceptual engineering blueprint system.

View the Complete HERPS System

Contact Blueprints Market for product, licensing and engineering-package enquiries.

HERPS VOL 22 FAT SAT COMMISSIONING PERFORMANCE ACCEPTANCE REV D R2.0
© Paul Smith — Alpha & Omega Limited — PlatformClouds.com — Conceptual Engineering Preview — Not Approved for Manufacturing

HERPS-VOL-22-FAT-SAT-COMMISSIONING-PERFORMANCE-ACCEPTANCE-REV-D-R2.0.webp