H.E.R.P.S — Materials, Fabrication, Welding, Surface Finish & Tolerances

HERPS-VOL-19 — Revision D R2.0

Hybrid Energy Recovery Pump System (H.E.R.P.S)

Revision D Manufacturing & Materials Baseline

HERPS-VOL-19 establishes the controlled design-development baseline for materials of construction, fabrication practice, welding control, examination, surface treatment, coatings, machining quality, dimensional tolerances, bolted-joint preload, identification, segregation, cleanliness, preservation and manufacturing records for the complete HERPS package.

The manufacturing specification preserves the locked hydraulic, mechanical, electrical, structural, thermal and package interfaces established by the wider HERPS Revision D engineering system.

Manufacturing Design Basis

Parameter Revision D Baseline
Machine 160 kW-drive-class horizontal three-stage variable-speed centrifugal industrial water pump with controlled hydraulic-energy-recovery path
Rated Duty 150 L/s at 80 m TDH
Rated Pump Speed 2,900 rpm
Main Water Pressure Boundary 25 bar(g) design
Design Temperature 80 °C
Hydrostatic Proof Baseline 37.5 bar(g), subject to governing code and material factors
Package Envelope 10,400 L × 2,600 W × 2,400 H mm maximum
Structural Base 10,400 L × 2,400 W × 300 mm deep

Revision D Materials Governance

Material substitution is not permitted solely on nominal strength equivalence. Any substitution affecting corrosion resistance, weldability, heat treatment, magnetic behavior, galvanic compatibility, fatigue, cavitation resistance, pressure-code compliance, mass, thermal expansion, electrical bonding or dimensional interfaces requires formal engineering review.

Unified HERPS Material Schedule

Component Family Revision D Material Manufacturing Function
Pump Casings / Main Wetted Pressure Parts Duplex Stainless Steel 2205 Primary corrosion-resistant pressure material
Impellers / Turbine Runner Super Duplex 2507 Cavitation and erosion-resistant rotating wetted components
Stage Diffusers / Interstage Casings Duplex 2205 Pressure and wetted fabrication
Turbine Housing / Guide-Vane Housing Duplex 2205 Pressure/wetted energy-recovery structure
Main Pump Shaft 42CrMo4 / AISI 4140 Class, Quenched & Tempered ≥700 MPa yield-strength basis
Turbine Shaft 17-4PH / Protected 4140 Corrosion-protected rotating shaft route
Shaft Sleeves 17-4PH or Super Duplex 2507 Replaceable wear/seal interfaces
Balance Drum 17-4PH + 2205 Sleeve Axial-thrust management component
Mechanical Seal Faces SiC / SiC Mechanical sealing surfaces
Main Process Piping Duplex 2205 DN350 / DN300 / DN300 main-water network
Small-Bore Process / Instrumentation 316L Stainless Steel Impulse, drain, flush and vent systems
Cooling System Wetted Components 316L Stainless Steel Closed cooling loop
Skid / Frame / Supports S355 Structural Steel Primary structural support architecture
Wetted Fasteners A4-80 / Suitable Duplex Corrosion-compatible pressure/wetted fastening
Guards 304 Stainless Steel 1.5–2.0 mm typical sheet where specified

Material Receipt, Traceability & Storage

Duplex 2205 & Super Duplex 2507 Fabrication

Duplex and super-duplex fabrication uses qualified procedures intended to preserve corrosion resistance, phase balance, toughness and pressure integrity while preventing carbon-steel contamination.

Carbon & Alloy Steel Fabrication

Stainless Process Piping Fabrication

Line Material / Size Service
L-101 Main Suction Duplex 2205 — 355.6 × 9.5 mm DN350, 25 bar main suction
L-201 / L-202 Discharge / Direct Duplex 2205 — 323.9 × 10.0 mm DN300, 25 bar
L-D301 Energy-Recovery Branch Duplex 2205 — DN300 25 bar, 0–150 L/s recovery path
L-302 Trim / Bypass 316L / 2205 — 114.3 × 6.0 mm DN100
L-401S/R Cooling 316L — 48.3 × 3.7 mm DN40, 6 bar closed loop
L-501 Drain 316L — 60.3 × 3.9 mm DN50 drain system
L-502 Seal Flush 316L — 21.3 × 2.8 mm DN15, 25 bar

Weld Category & Quality-Level Matrix

Category Application Minimum Control
W1 — Pressure Boundary Critical Pump casings, pressure heads, DN350/DN300 process welds and turbine pressure housing Qualified WPS/PQR, qualified welder, full VT and required surface/volumetric examination
W2 — Wetted Non-Primary / Small Bore 316L flush, drain, cooling and instrumentation connections Qualified procedure, VT and appropriate leak/pressure test
W3 — Rotating-Component Repair Impeller, runner or shaft repair only where specifically engineered No weld repair by default; engineering disposition required
W4 — Primary Structural Main rails, crossmembers, lifting lugs, anchor pads and major supports Approved structural WPS, VT and additional examination where required
W5 — Secondary Structural / Guards Guard frames, tray brackets and noncritical supports Controlled workmanship and visual examination

Weld Joint Preparation & Execution

NDE & Examination Baseline

Examination Revision D Application
VT — Visual Testing 100% pressure-boundary and structural weld baseline workmanship examination
PT — Liquid Penetrant Critical duplex pressure-weld surfaces and relevant stainless areas
UT / RT Pressure-boundary welds as determined by category, geometry and governing code
MT Carbon/alloy structural or lifting welds where required
Dimensional Inspection Locked interfaces, shaft features, casing joints, datums, flanges and package envelope
PMI Critical alloy identity verification where required by the quality plan

Pressure Testing, Leak Testing & Cleanliness

Pickling, Passivation & Stainless Surface Restoration

S355 Carbon-Steel Coating System

Layer / Control Revision D Baseline
Substrate S355 skid, frame and structural supports
Preparation Blast-cleaned to approved coating specification
Primer Zinc-rich epoxy primer
Intermediate High-build epoxy
Topcoat Polyurethane
Total DFT 250–350 µm baseline

Machined Surface Finish Requirements

Feature Revision D Requirement
Pump Shaft Journals Ra ≤ 0.4 µm
Seal Track / Sleeve Ra ≤ 0.4 µm
Fatigue-Critical Shaft Fillets Ra ≤ 1.6 µm; polished transitions
General Machined Surfaces Ra ≤ 1.6 µm unless function requires otherwise
Non-Machined Pressure Surface Ra ≤ 6.3 µm or applicable manufacturing standard
Casing Joint Faces Flatness ≤ 0.05 mm per 300 mm; ≤ 0.15 mm total
Flange Faces Flatness ≤ 0.15 mm
Base Mounting Pads Flatness ≤ 0.10 mm across each foot set
Motor / Pump Skid Datums Coplanarity before shims ≤ 0.25 mm

Dimensional & Geometric Tolerances

Feature Tolerance / Limit
Machined Dimensions ≤500 mm ±0.10 mm unless fit stated
Machined Dimensions >500–2,000 mm ±0.20 mm
Fabricated Skid Overall ±2.0 mm
Pump Shaft Total Length 1,600 ±0.20 mm
Shaft Straightness ≤0.03 mm over 1,600 mm
Journal TIR ≤0.015 mm
Assembled Rotor TIR at Impeller OD ≤0.05 mm
Impeller Axial Runout ≤0.03 mm
Impeller Bore 80 H7
Shaft Impeller Seats 80 h6
DE / NDE Bearing Journals 70 k6
Final Shaft Alignment Parallel ≤0.05 mm; angular ≤0.05° with hot-growth correction
Rotor Balance G2.5 or better, subject to final validation release

Rotating-Component Manufacturing Quality

Bolted Joint, Torque & Preload Policy

HERPS does not apply a universal torque value across the machine. Controlled joints use joint-specific tightening requirements based on fastener material, lubrication, gasket condition, coating, washers and required clamp load.

Galvanic Isolation & Mixed-Metal Interfaces

Permanent Identification & Traceability

Hose, Tubing, Cable & Conduit Segregation

System Cleanliness Requirements

Fabrication Dimensional Control & Datum Transfer

Manufacturing inspection references the Revision D machine coordinate system: X downstream along the machine, Y left when viewed from the intake, and Z upward from the skid datum.

Locked Interface Coordinate
Pump / Motor Shaft Centreline Y = 0 / Z = +800 mm
Turbine / Generator Shaft Centreline Y = +950 / Z = +850 mm

Manufacturing Hold & Witness Points

Manufacturing Quality Data Book

Validation-Controlled Manufacturing Requirements

Revision D deliberately does not falsely freeze manufacturing parameters that require final code calculations, qualified procedures, vendor information, structural analysis or site-specific engineering.

Revision D Engineering Status

HERPS-VOL-19 Revision D R2.0 is a consolidated master design-development manufacturing baseline. It provides coordinated CAD and fabrication input while retaining the validation gates required before IFC, shop or final production release.

Final qualified welding variables, code-specific examination requirements, structural weld sizing, purchased-component dimensions, joint preload values, site coating requirements and other validation-controlled values remain subject to their governing engineering release processes.

Explore the Complete H.E.R.P.S Revision D System

Materials, Fabrication, Welding, Surface Finish & Tolerances forms part of the complete H.E.R.P.S Revision D multi-volume conceptual engineering blueprint system.

View the Complete HERPS System

Contact Blueprints Market for product, licensing and engineering-package enquiries.

HERPS VOL 19 MATERIALS FABRICATION WELDING SURFACE FINISH TOLERANCES REV D R2.0
© Paul Smith — Alpha & Omega Limited — PlatformClouds.com — Conceptual Engineering Preview — Not Approved for Manufacturing

HERPS-VOL-19-MATERIALS-FABRICATION-WELDING-SURFACE-FINISH-TOLERANCES-REV-D-R2.0.webp