H.E.R.P.S — HYBRID ENERGY RECOVERY PUMP SYSTEM

Structural Skid, Equipment Supports, Guards & Lifting

HERPS-VOL-17 — Revision D R2.0

The H.E.R.P.S Revision D structural package is built around one continuous 10,400 mm S355 structural skid supporting the complete hydraulic, rotating, thermal, electrical, energy-storage and control package.

Volume 17 controls the primary structural rails and crossmembers, pump and motor mounting interfaces, recovery turbine and PMG rails, large-bore piping and valve supports, thermal rack, electrical deck, vibration isolation, guarding, lifting and tie-down provisions, anchor pads, bonding interfaces and structural load paths.

Engineering Status: Master Design-Development — CAD / FEA / Procurement Input Subject to Revision D Validation Gates — Not Released for Construction

Revision D Structural Identity

Complete Package Envelope

10,400 L × 2,600 W × 2,400 H maximum.

Structural Base

10,400 L × 2,400 W × 300 deep.

Pump / Motor Axis

Y=0, Z=+800.

Recovery Turbine / PMG Axis

Nominal Y=+950, Z=+850.

Lift Design Mass

13,500 kg minimum until actual approved lift-state mass is frozen.

Structural Equivalent Mass

18,000 kg including dynamic and handling allowance.

Primary Structural Frame

Structural Item Quantity Revision D R2.0 Baseline
Main longitudinal rails 2 S355 RHS 250×150×10; length 10,400 mm
End cross rails 2 S355 RHS 250×150×10; width 2,400 mm
Primary crossmembers 15 S355 RHS 200×100×8; approximately 2,100 mm clear; ≤750 mm nominal spacing
Pump mounting plates 4 S355 plate 300×220×25; machined top
Motor mounting rails 2 S355 1,200×180×30; machined top
Recovery turbine / PMG rails 2 S355 1,800×120×20 baseline
Valve / manifold supports As required S355 RHS 100×100×6 minimum before final support calculation

Structural Load Distribution

The two 10,400 mm longitudinal rails act as the principal package beams. The two end rails and fifteen primary crossmembers form one continuous full-package structural base.

Rotating equipment, DN350/DN300 piping and valves, the recovery train, thermal hardware and electrical/BESS cabinets transfer dead, operating, transient, service and handling loads through dedicated supports into the primary skid.

Pump and turbine nozzles and instrument connections are not used as structural supports. Large valves, vertical piping runs and other concentrated masses require independent support.

Pump & Motor Support System

Pump Plates

Four 300×220×25 mm S355 machined mounting plates.

Motor Rails

Two 1,200×180×30 mm S355 machined rails for the Revision D 160 kW liquid-cooled SynRM baseline.

Mounting Datums

Finish-machined after skid welding and structural stabilization.

Pump/Motor Coplanarity

≤0.25 mm before shimming.

Foot-Set Flatness

≤0.10 mm.

Final Alignment

Parallel ≤0.05 mm and angular ≤0.05° with hot-growth correction.

Motor removal requires at least 1,500 mm unobstructed clearance, and permanent DN300 piping must not pass above or through the motor removal axis.

Recovery Turbine & PMG Support System

Revision D supersedes the earlier DN250 support concept with a DN300 recovery branch and DN300 axial/Kaplan-inspired recovery cartridge.

Recovery Rails

2 × S355, 1,800×120×20 mm baseline.

Recovery Axis

Nominal Y=+950, Z=+850.

GA-D06 Zone

X=2,500–5,300; Y=+700..+1,250; Z=450..1,450.

Recovery Cartridge Removal

≥1,200 mm toward +Y.

PMG Pull Clearance

≥800 mm local clearance.

Load Isolation

Piping loads are isolated from the turbine cartridge and PMG train.

DN350 / DN300 Piping & Valve Support System

Service Revision D Line Structural Rule
Intake DN350 Duplex 2205 Independent support; preserve Y0/Z800; no pump-nozzle weight
Common discharge DN300 Duplex 2205 Independent riser/header/valve supports
Direct path DN300 Duplex 2205 Support valves/check devices without nozzle loading
Recovery branch DN300 Duplex 2205 Independent branch support to turbine throat and rejoin
Cooling DN40 316L Preserve service access and drainability
Drain / seal flush DN50 / DN15 Support without instrument or root-valve interference

Thermal Rack Structure

The Revision D thermal rack occupies GA-D07, approximately X=6,000–7,500, Y=+250..+1,200 and Z=300..1,900.

The baseline rack uses S355 RHS 80×80×6 with an approximate 1,600×1,000×1,600 mm envelope.

It supports the 40 kW radiator, two EC fans, 40 kW plate heat exchanger, duty/standby VSD coolant pumps, 50 L expansion tank, 80 L reservoir, filter and DN40 thermal interfaces.

Electrical Deck & Cabinet Supports

The Revision D electrical deck extends approximately from X=6,000 to X=10,400 across the 2,400 mm structural width.

GA-D08

AFE/VFD — X=6,000–7,200.

GA-D09

Switchgear / control — X=7,200–8,100.

GA-D10

DC / supercapacitor — X=8,100–8,900.

GA-D11

BESS A — X=8,900–9,500.

GA-D12

BESS B — X=9,500–10,100.

Cabinet fronts require at least 1,200 mm external clear space, or greater where required by applicable codes.

Vibration Isolation

Parameter Revision D R2.0 Basis
Quantity 12
Type Spring / elastomer
Static Capacity ≥25 kN each
Target Static Deflection 8–12 mm
Final Selection Vendor + D-G17 structural validation

The isolators are package-support elements and are not substitutes for internal skid stiffness.

Guarding System

Pump / Motor Coupling Guard

304 stainless steel, 2 mm perforated baseline, tool-removable.

Turbine / PMG Coupling Guard

304 stainless steel, 1.5–2.0 mm baseline.

Fan / Auxiliary Guards

304 stainless steel or OEM-compliant guarding.

Guard Support

Skid/rack-mounted and arranged so rotating housings are not distorted.

Lifting, Tie-Down & Handling

Primary Lifting Lugs

4.

Auxiliary Lift / Tie-Down Lugs

2.

Minimum Lift Design Mass

13,500 kg.

Planning CG Target

X=4,800–5,600; |Y|<200; Z<950.

Lift Arrangement

Four-point primary lift baseline.

Final Release

D-G17 lifting calculation and controlled lift drawing / plan required.

Primary lifting reactions must enter the principal rail/crossmember load paths. Deck plate alone is not permitted to carry a primary lift reaction.

Anchor Pads & Foundation Interface

Feature Revision D R2.0 Basis
Anchor Pads 16 × S355 plate 180×140×25
Slots 34×60 mm for M30 concept anchors
Anchor Rows Y=±950
Anchor X Coordinates 400, 1,800, 3,200, 4,600, 6,000, 7,400, 8,800, 10,000
Foundation Planning Envelope 11,200 L × 3,400 W × 400 thick minimum
Concrete Planning Baseline ≥35 MPa
Grout 25–50 mm non-shrink machinery grout

Volume 17 controls the skid-side anchor pads, slots and reaction handoff. Final anchor product, grade, embedment, reinforcement, concrete breakout, seismic verification and site foundation design remain controlled by Volume 18 and site engineering.

Structural Materials, Coating & Galvanic Isolation

Component Family Material / Finish
Primary skid / frame / supports S355 structural steel
Structural coating Zinc-rich epoxy + high-build epoxy + polyurethane
Coating thickness 250–350 µm DFT baseline
Guards 304 stainless steel, 1.5–2.0 mm family
Dry structural fasteners Class 10.9 zinc-flake or engineered corrosion-resistant
Duplex-to-S355 interfaces Nonconductive isolation where required

Fabrication & Dimensional Control

Fabricated Skid Overall

±2.0 mm baseline unless released drawing is tighter.

Pump / Motor Coplanarity

≤0.25 mm before shims.

Foot-Set Flatness

≤0.10 mm.

Alignment-Zone Rail Deflection

L/1000 or 2 mm, whichever is more stringent.

Mounting Datums

Finish-machine after welding and stabilization.

Final Survey

As-built X/Y/Z supports, elevations, flatness, anchor pads, lift points and package mass/CG.

Service & Removal Clearances

Service Requirement Minimum Clearance
General side access ≥1,000 mm outside package
Pump shaft / cartridge pull ≥2,000 mm
Motor removal ≥1,500 mm
Recovery cartridge ≥1,200 mm toward +Y
PMG local pull ≥800 mm
Cabinet front ≥1,200 mm or code greater
Radiator face ≥600 mm
Seal cartridge ≥250 mm
Bearing housing ≥400 mm
Valve actuator ≥300 mm beyond envelope or OEM greater

Real-World Structural Build Sequence

  1. Close the Revision D vendor/CAD interfaces and structural-design inputs.
  2. Fabricate the two 10,400 mm main rails, two 2,400 mm end rails and fifteen primary crossmembers in a controlled fixture.
  3. Install released local reinforcement, anchor-pad framing, support stools and lift-load-path members.
  4. Complete structural welding using the approved sequence.
  5. Perform post-weld dimensional survey and finish-machine pump plates and motor rails after structural stabilization.
  6. Fabricate and install the Revision D thermal rack and electrical deck framing.
  7. Blast-clean and coat the carbon-steel structural assembly.
  8. Install the twelve selected vibration isolators after reaction and stiffness approval.
  9. Mount the pump at Y0/Z800 and the selected 160 kW motor and establish preliminary alignment.
  10. Install the DN350 intake and DN300 common/direct/recovery support system with independent piping load paths.
  11. Install the DN300 recovery turbine/PMG support rails and verify cartridge and PMG withdrawal clearances.
  12. Install thermal equipment and electrical/DC/BESS cabinets while preserving service clearances.
  13. Install guards and structural brackets and verify non-contact clearance under vibration, misalignment and thermal growth.
  14. Install protective bonding straps and verify continuity.
  15. Complete final piping-connected pump/motor and turbine/PMG alignment and nozzle-strain checks.
  16. Freeze approved as-built masses and coordinates and complete the structural FEA, lift analysis, final CG, isolator reactions and lift plan.
  17. Issue final anchor-pad reactions to the foundation design.
  18. Complete FAT/SAT structural, guarding, bonding, alignment and documentation acceptance.

Structural FEA, Lifting & Validation

The Revision D structural validation includes dead load, rotating loads, DN350/DN300 piping and valve loads, electrical/BESS loads, handling and lifting, structural-equivalent mass, anchor/foundation reactions, maintenance loads, site seismic/wind and modal/stiffness load cases.

Final weld sizes, local gusset geometry, lift-lug reinforcement and WLL, isolator stiffness/damping, actual package mass and centre of gravity, final cabinet base patterns, local recovery-support geometry, anchor/foundation capacity and seismic/wind response remain validation-, OEM- or site-controlled and are not fabrication-final.

Master Design-Development — Not IFC — Not Shop Release — Not Approved for Manufacturing.

VOLUME 17 — STRUCTURAL SKID / EQUIPMENT SUPPORTS / GUARDS / LIFTING

HERPS VOL 17 Structural Skid Equipment Supports Guards and Lifting Revision D R2.0
© Paul Smith — Alpha & Omega Limited — PlatformClouds.com — Conceptual Engineering Preview — Not Approved for Manufacturing

HERPS-VOL-17-STRUCTURAL-SKID-EQUIPMENT-SUPPORTS-GUARDS-AND-LIFTING-REV-D-R2.0.webp